20 — Changes, anomalies, retests and qualification credit
DO-160 Display Qualification | A-P02 — Draft / Not Released
Learning objective: Preserve evidence and select regression work after a display change.
Image: Radarvector; source crop by Pittigrilli · Keysight InfiniiVision DSOX 4024A and digital multimeter and power supply in laboratory use · CC BY-SA 4.0. Existing source crop by Pittigrilli retained; no further image edits. Displayed at reduced size.
Qualification follows a configuration
DO-160G §2.9 connects results to the tested configuration. When design changes could affect the results, substantiate applicability or perform affected testing. Review changes in panel technology, backlight power, optical bond, cover coating, touch electronics, firmware, shielding, enclosure, cooling and harness. A nominally equivalent resolution and size do not establish environmental equivalence.
A practical change review
- Identify the exact old and new configuration, including manufacturing process changes.
- List affected physical, electrical, thermal and functional mechanisms.
- Map each mechanism to requirements and previous evidence.
- Decide what can be credited and why; define development checks and qualification retests where needed.
- Record the disposition, resulting installation limits and effect on delivered or supported units.
Anomaly record
Record time, test stage, applied condition, unit identity, mode, observations, raw data links, immediate action and equipment state. Distinguish an equipment failure from a laboratory setup problem through investigation, not assumption. Retain the original result even after successful repair and retest.
Worked change example
A new touch controller reduces false touches but uses a different clock and scan scheme. The optical appearance is unchanged. Review RF emissions/susceptibility, ESD response, power loading and control behavior. Temperature and materials evidence may also be affected if the electronics or construction changes. The retest scope follows this assessment; it is neither automatically every test nor automatically no test.
Exercise
The unit fails cold startup, receives a firmware workaround and passes at room temperature. Is the cold requirement closed? Worked response: no. Reverify the affected cold condition and any related behavior or regression scope established by the change assessment. Confirm that the workaround does not trade the startup failure for misleading imagery, excess warm-up delay or an unannunciated degraded mode.
Report the final baseline
The final report identifies the as-tested and accepted configuration, deviations, unresolved limitations and the trace from failed to retested requirements. Update the qualification summary and installation instructions consistently. A clean summary must not erase the development or qualification history needed to understand the evidence.